Current Roadway Capital Projects
Reconstruction / New Construction

  Schedules presented in following updates    may vary depending on weather conditions.

                   Location/Description

Phase IIID: Taylor Street Re-construction Project

This project includes removing and replacing the damaged sub-grade and concrete pavement and existing damaged concrete curb and gutter at various locations along Taylor Street between the intersection with North Colony Boulevard to the intersection with Squires Drive. After these repairs have been made, the concrete roadway surface will be milled down 1-inch and a 2-inch thick asphalt pavement overlay will be installed along roadway. Any questions about the project can be directed to the Engineering Department at 972-624-3195 or at the following e-mail.  engineering@thecolonytx.gov

Update:

  • The contractor has completed milling the concrete street.
  • The asphalt will be placed the first week of August.
  • Removal and replacement of sidewalks is complete.
  • Construction will be substantially complete before school starts back in the fall. This construction period was chosen to minimize impacts on the traffic flow to and from BB Owens Elementary School.
  • The construction project was bid in April 2010 and City Council Approved the Contractor in May 2010.
  • A public information meeting was held in May 2010.
  • Final engineering plans were completed in April 2010.

 

North Colony Boulevard Widening Project

On October 20, 2009, the City Council authorized design of the North Colony Boulevard widening project by Halff Associates, Inc. The widening project consists of a four lane divided roadway with auxiliary left and right turn lanes and trail from Curry Drive to Paige Road. Other improvements that will be constructed with this project include drainage, water, wastewater, streetscape, traffic signals, sidewalk repair, slip-road repair, and new street lights.

Construction activities are anticipated to start in October 2010 and be substantially complete by March 2012. The budget for construction of this project is $6.8 million.

The Engineering Department will continue to post updates and information concerning the progress of this important project in the Updates section below.  If you have any questions, please contact the Engineering Department at 972-624-3195 or at the

e-mail below.

engineering@thecolonytx.gov

 

Helpful Links:

Update:

  • Final construction plans are being prepared.
  • Proposed plans were presented to City Council on June 15, 2010.
  • A public information meeting was held in May 2010.

 

STEWART CREEK PARK PAVEMENT RESURFACING

On May 18, 2010, the City Council authorized the resurfacing of the roadways and parking lots within Stewart Creek Park. The work consisted of making necessary base repairs and overlaying the roadways and parking lots with hot mix asphalt .

The Engineering Department will continue to post updates and information concerning the progress of this important project in the Updates section below.  If you have any questions, please contact the Engineering Department at 972-624-3195 or at the

e-mail below.

engineering@thecolonytx.gov

 

Update: 

  • Construction began on May 26, 2010 and was completed on June 25, 2010.
  • The boat trailer parking area stripping is complete.

 

LEBANON ROAD DRAINAGE REPAIRS

 

.

Update: 

  • Tunnel repairs and the pavement lifting have been completed.
  • Drainage from Boyd Road is complete.
  • The Contractor has completed routing and sealing cracks.
  • The curb and pavement replacement have been completed.

 